In summary
  • The Obeya Room is a physical or digital space where the status, priorities, issues, and KPIs of the projects remain visible and the functions decide at regular intervals.
  • Born in Toyota in the 1990s with the first Prius, the Obeya is now also used in machinery, components, pharmaceuticals and plant engineering projects on commission.
  • An Obeya works only with three conditions: up-to-date information from those working on the project, a fixed rhythm of meetings, and decisions made in the room.
  • The four walls are portfolio management with finite capacity, Kanban and Project Board, project KPIs (Lead Time and On Time), issues, and A3.
  • We start with a small scope, with two walls on paper and a weekly meeting for 2–3 months, and only after that do we consider going digital.
Index

The Obeya Room is a space, physical or digital, where the status, priorities, issues, and KPIs of the projects remain always visible. And the people from the different functions involved meet on a regular basis to decide. So the problems between one function and the other emerge in a few days, not at the end of the phase. The term comes from the Japanese word “grande stanza”, and it was born in Toyota’s product development.

In the development of a new product, R&D, technical office, purchasing, quality, production and marketing work together. Each of these functions works well within its own scope, but the project lives in the spaces between one function and the next: that is where delays arise.

Why product development projects stall (even with good people)

Anyone who manages a technical area immediately recognizes the symptoms: all projects are “of high priority,” the launch dates are slipping, the same people are working on five or six projects together. No one is working poorly, Yet the system produces delays on a regular basis.

In Lean Development projects What we follow: the cause is rarely technical. A company’s development capacity depends on three elements combined: processes, Governance e resources. When interventions are limited to resources (more people, more extraordinary efforts) without touching upon processes and governance, delays are moved but do not disappear. We discussed this in the article on Lean R&D and delays in product development.

Two mechanisms weigh more than others. The first are the interfacesA project goes through dozens of functions and at each step there is a wait or a change that someone hasn’t seen. Taken one by one they are small delays; added up they amount to weeks, and no one sees them until they become serious.

The second is the The rhythm of decisions. If the status of projects is discussed in the monthly committee, based on reports prepared days earlier, a problem reaches management when it has already been several weeks old. The Obeya intervenes on both: it makes the flow between functions visible and shortens the time between a problem and a decision.

What is the Obeya Room (and what it is not)

The Obeya is the place where the visual management tools for projects find their full effectiveness. Tables, plans and KPIs do not remain locked in a file to be opened when needed: they are exhibited permanently on the walls, and the project team meets there. The room becomes an always up-to-date report: just walk in to see where the projects are at, where the problems are, and who is handling them.

There is one aspect that matters even more. In an Obeya, experts from the different departments work together. They stop being representatives of their office and become a Project teams. The designer, the purchasing manager and the quality manager all look at the same wall and discuss the same problem. It’s not a side effect: it’s the main reason why the room works.

The idea originated at Toyota in the 1990s, with Development of the first Prius. The project manager brought together the heads of the various technical departments in a single large room. Since then, Obeya has moved away from automotive and is now used in very different sectors: machinery, components, materials, pharmaceuticals, and commissioned plant construction.

It's not a meeting room with posters on the walls.

The most common mistake is to think that it’s enough to hang a Gantt chart and some graphs in a room. An Obeya is not defined by its walls, but by three things:

    • the information is updated, At least at each meeting, from those working on the project;
    • there is a fixed rhythm of meetings, with defined schedules, duration and participants;
    • in the room the decision is made: priorities, allocation of resources, actions on open issues.

If even one of these elements is missing, the room becomes a gallery of posters that no one looks at after the first month.

The connection with the other tools of Visual Management

The Obeya belongs to the family of Visual Management, the same as those of the department boards and the Daily Management. The logic is identical: make the state of the work visible so that problems emerge immediately and people can act. The difference is the object: in production shifts, parts and stops are managed; in the Obeya, projects, phases and decisions are managed.

What is on the walls of an Obeya that works

There is no one-size-fits-all configuration: the walls change with the number of projects, their duration, and the sector. However, in the projects we follow, we almost always find four areas.  

THE FOUR WALLS OF A OBEYA

1

Project portfolio

Family of projects, priorities and limits to open projects: a project only starts when capacity is freed up.

2

Kanban and Project Board

A project board with phases, deadlines, responsible person, and delays; details about the next 4–6 weeks.

3

Project KPIs

Few updated indicators at each meeting: Lead Time and On Time to start.

4

Problems and A3

Every blocking problem has a responsible person and a date; the most complex ones are analyzed using an A3.

Wall 1 – The portfolio of projects with completed capacity

The first wall answers the question “how many projects can we really carry out?”. The projects are grouped into families and are classified according to complexity and strategic importance. The portfolio is then managed to finite capacityThere is a limit to open projects at the same time, and a new project only enters when another one closes.

It's the most uncomfortable wall, because it forces you to say no. And it is the one that produces the greatest results: reducing the number of projects in parallel is the fastest way to shorten each one's travel time.

Wall 2 – The Portfolio Kanban and the Project Board

The second wall shows the progress. The Kanban of wallet gives an overview: a project card in the column of the phase in which it is located. The Project Board details the individual project over the 4–6 weeks following, with the activities of each function.

Six pieces of information are enough on each sign:

  • name of the project;
  • ongoing phase;
  • next milestone and date;
  • responsible;
  • State: green, yellow or red;
  • blocking problem, if there is one.

For very short projects, the Project Board is not necessary. It becomes indispensable for complex or iterative projects, where the planning changes as new information is discovered.

Wall 3 – The project KPIs

The third wall measures. The two indicators to start from are: Lead Time (how long does a project take to go through the phases) and On Time (how many projects, or milestones, meet the planned date). Better a few updated indicators at each meeting than a complete dashboard that no one reads.

Wall 4 – Open issues and A3

The fourth wall is that of the problems. Every problem that blocks a project has a responsible person, a date, and a status. The most complex problems are tackled with an A3, The report on a single sheet that summarizes the context, analysis of the causes, countermeasures, and verification. Here, the Obeya connects to knowledge management: the closed A3s become reusable knowledge in subsequent projects.

Routine and meetings: the rhythm that keeps the room running

A routine-free Obeya lasts only a few weeks. The rhythm of the meetings is what transforms the walls into decisions.

The project manager and a representative from each involved function (R&D, technical office, purchasing, quality, production) participate; the management team is involved in the monthly review of the portfolio.

The weekly meeting of the project team

It is the heart of the system. Once a week the project team meets in front of the Kanban: for each card they look at what has been done, what is behind schedule and what needs to be done to get it back on track. Immediately after each function they plan the next week. to finite capacity, That is, about the actual hours available to people, and not just about deadlines. Approximate duration: 45–60 minutes, standing in front of the walls.

The short point about the problems

Between one weekly meeting and the next, a quick moment of 15 minutes is needed, Dedicated only to open issues and those to be brought to management. The status of all projects is not discussed; the wall of issues is looked at and a decision is made about who does what within a specific timeframe. If a problem exceeds the team level, it is escalated to the next management meeting with a specific date.

The portfolio review with the management

Once a month, or at each closure of an important phase, The management enters the Obeya. Here they decide what the team cannot decide on its own: which projects to start or suspend, how to move resources, which risks to accept. The difference compared to a classic committee is that the discussion takes place in front of the walls, on the updated data, and not on prepared slides for the occasion.

AN EXAMPLE OF PROPORTIONAL GOVERNANCE

Kerakoll Group has revised the process of developing new products with Bonfiglioli Consulting with an “incremental protection” approach: four levels of governance, calibrated to the strategic importance of each project. The goal, explains Gabriele Retucci, chief marketing officer of the group, is leadership “with greater intensity where the risk is higher, and greater agility where the impact is less.” This is the difference that an Obeya must make visible.

→ Read the Kerakoll case as told by Technopolis

Physical or digital office: how to choose

With teams distributed across multiple locations, the demand arrives quickly: does a room really need to be set up? The answer depends on the organization, but experience suggests a precise process.

In a visual planning project at a client, we started deliberately simply: handwritten sheets and post-its to verify that the system was working. Once the method was established, the system moved to a printed board with standard labels. Then came a metallic grid with printed labels and finally a digital version on a touch screen. Each step came when the previous one had become a habit.

The lesson is simple: First the method, then the instrument. Better a few weeks of paper and post-it notes: you can see what is really needed and avoid paying for features that no one will use. Digitizing an Obeya that doesn’t work only creates a more expensive problem.

  Physical Obey Digital Obey Hybrid Obeya
When to choose it Team in the same location, launch of the method Teams distributed across multiple locations or countries Headquarters plus colleagues connected remotely
Strengths Immediate visibility, direct comparison, minimal costs Access from anywhere, data linked to corporate systems, history It keeps the room as a place of decision and includes those who are far away.
Risks Excludes those who are not in the office; manual update The walls become screens that no one opens Two versions to keep in line
Requirement to operate A tried-and-tested method, a fixed rhythm of meetings and decisions taken in front of the walls

The most common mistakes (and how to avoid them)

Three mistakes occur more often than others:

  • Putting everything on the walls that is there. A wall full of graphics is no longer clear; it is more confused. Every element displayed must answer a question that the team asks at every meeting; the rest can remain in the corporate systems.
  • Leaving the walls to just one “secretary”. If updating is the responsibility of only one person, the information ages and the team stops feeling it as their own. Each responsible updates their own labels.
  • Use the room to check, not to decide. When the Obeya becomes the place where guilty parties are sought, people stop reporting problems in advance. A delay seen early is a delay that can still be recovered.

What results to expect

The effects of a well-managed Obeya are seen on two levels. The first It is the project: Planning is done at the level of detail needed; problems between functions emerge early and dates remain at the center of meetings. The second is people: mutual trust grows and the project becomes the responsibility of the entire team, not just the project manager.

These are effects that do not depend on the room itself, but on the system that makes the room visible and manageable: processes, governance, and the resources of the development product.

Where to start

The first step is not to set up a room, but to choose a perimeter. A path that works:

  1. Choosing the perimeter: a family of projects and a team, not the entire company.
  2. Construct two paper walls (Weeks 1–2): portfolio and Kanban, with handwritten labels.
  3. Schedule the weekly meeting: date, time, duration and participants, in front of the walls.
  4. Keep it for 2–3 months Before adding anything else: KPIs and the problem wall come when the rhythm has become habitual.
  5. Extending and evaluating the digital: other projects, other locations, then the instrument.

If you are considering how to make your product development more rapid and predictable, the service Innovation & Product Development Bonfiglioli Consulting assists companies in redesigning processes, governance, and visual tools. To learn how to manage projects using the Lean principles, there is the Lean Factory School® course. Project Management.

The Innovation & Product Development courses of the Lean Factory School® They bring the method to the technical office: Lean management of the order, Design Thinking, FMEA, Robust Design and design techniques to reduce product costs.

Frequently Asked Questions

What is the Obeya Room and what is its purpose in product development?

The Obeya Room, from the Japanese “large room”, is a physical or digital space where the status, priorities, problems, and KPIs of projects are always visible. The involved functions, such as R&D, technical office, purchasing, quality, and production, meet on a regular basis to decide. Thus, problems between functions emerge within a few days, not at the end of the phase.

What elements should be present on the walls of an Obeya Room to manage projects?

An effective Obeya always has four walls: a project portfolio with a limit on open projects, a Kanban portfolio with the Project Board for the next 4–6 weeks, a few project KPIs such as Lead Time and On Time, and an open issues wall with A3s for the most complex cases.

How often does the team of an Obeya Room meet and who participates?

The team meets once a week for 45–60 minutes, standing in front of the Kanban with the project manager and a representative for each function. Between meetings there is a brief 15-minute break to discuss open issues. Management participates in the monthly portfolio review or any important phase closure.

Is a physical, digital, or hybrid Obeya better for a team distributed across multiple locations?

For teams in the same location, the physical Obeya method is suitable; for teams in multiple locations or countries, the digital method is more suitable. If there is a main office with remote colleagues, a hybrid method is used. In any case, the method is first consolidated, starting with paper and post-it notes, then the digital tool is chosen.

What are the most common mistakes when introducing an Obeya Room in a company?

The most frequent mistakes are three: displaying everything on the walls, entrusting the updating to only one secretary, and using the room to check and find guilty parties instead of deciding. Each item displayed must answer a recurring question from the team, and each responsible updates their labels.

How do you start an Obeya Room in a company that develops new products?

We start by choosing a limited scope, that is, a family of projects and a team, not the entire company. In the first 1–2 weeks, two walls are prepared on paper: portfolio and Kanban, then the weekly meeting is scheduled and held for 2–3 months. Only after that do we add KPIs, the problem wall, and possibly a digital one.